Amendment sch3035a-1

sch3035a-1 sch3035a-1

1.1Senator Dibble moved to amend H.F. No. 3035, as amended by the Senate March
1.29, 2022, as follows:
1.3(The text of the amended House File is identical to S.F. No. 2676.)
1.4Page 3, line 21, before "Annually" insert "(a)"
1.5Page 3, after line 28, insert:
1.6"(b) The Metropolitan Council must notify the chairs and ranking minority members of
1.7the legislative committees with jurisdiction over transportation policy and finance within
1.8seven calendar days of making a determination that:
1.9(1) the anticipated Southwest light rail project completion date is delayed by six months
1.10or more beyond the estimated completion date determined as of the effective date of this
1.11section;
1.12(2) the anticipated Southwest light rail project completion date is delayed by six months
1.13or more beyond the most recent estimated completion date;
1.14(3) the total Southwest light rail project cost is anticipated to increase by five percent
1.15or more above the project cost estimate determined as of the effective date of this section;
1.16or
1.17(4) the total Southwest light rail project cost is anticipated to increase by five percent
1.18or more above the most recent cost estimate."
1.19Amend the title accordingly
1.20The motion prevailed. #did not prevail. So the amendment was #not adopted.